6th Street Overcrossing - Roadwork |
Description: Split Overcrossing project into two phases. Road and Bridge phases. This is the road word piece of the project.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | |
Senate District |
06 |
Assembly District | 09 |
Congressional District | 05 |
Caltrans District |
03 |
County/State Route | Sacramento na |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Carlos Ruiz | (916) 654-3894 | carlos.ruiz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$7,865 | $-714 | $7,151 | ||||
Non-bond Funding | |||||||
Local** |
$7,865 | $0 | $7,865 | ||||
Total**** | $15,730 | $-714 | $15,016 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,340 | $0 | $1,340 | $1,095 | $1,095 | $245 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$14,390 | $-714 | $13,676 | $12,787 | $12,787 | $889 | |
Total* | $15,730 | $-714 | $15,016 | $13,881 | $13,881 | $1,135 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/10/2006 08/20/2007 |
01/21/2011 01/21/2011 |
03/10/2006 08/20/2007 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/11/2008 08/11/2010 |
01/21/2011 01/21/2011 |
03/11/2008 08/11/2010 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
05/01/2009 04/30/2010 |
03/28/2012 03/28/2012 |
05/01/2009 04/30/2010 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/08/2012 02/08/2013 |
03/28/2012 03/28/2012 |
12/08/2012 06/28/2015 |
99 | 11/15/2012 04/15/2013 |
1 27 |
Begin Closeout Phase
End Closeout Phase |
02/09/2013 08/13/2013 |
03/28/2012 03/28/2012 |
02/09/2014 08/13/2014 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.