6th Street Overcrossing - Roadwork

Description: Split Overcrossing project into two phases. Road and Bridge phases. This is the road word piece of the project.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
 
County/State Route Sacramento na
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$7,865 $-714 $7,151
Non-bond Funding
Local**
$7,865 $0 $7,865
 
Total**** $15,730 $-714 $15,016

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,340 $0 $1,340 $1,095 $1,095 $245
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$14,390 $-714 $13,676 $12,787 $12,787 $889
 
Total* $15,730 $-714 $15,016 $13,881 $13,881 $1,135

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/10/2006 

08/20/2007 
01/21/2011 

01/21/2011 
03/10/2006 

08/20/2007 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/11/2008 

08/11/2010 
01/21/2011 

01/21/2011 
03/11/2008 

08/11/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
05/01/2009 

04/30/2010 
03/28/2012 

03/28/2012 
05/01/2009 

04/30/2010 
100   

 


Begin Construction Phase

End Construction Phase
02/08/2012 

02/08/2013 
03/28/2012 

03/28/2012 
12/08/2012 

06/28/2015 
99  11/15/2012 

04/15/2013 


27 
Begin Closeout Phase

End Closeout Phase
02/09/2013 

08/13/2013 
03/28/2012 

03/28/2012 
02/09/2014 

08/13/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.